[ARCHIVED] NEW! Upcoming Planning Items

News Flash Planning (1080x1620) (1)

UPCOMING LARGE PROJECTS

Mogul Capital Building on Cache


ABOUT: Mogul Capital submitted design plans for five separate buildings at 335 North Cache Street. The proposed Mogul hotel and condominium project is on 2.46 acres on N. Cache and includes 109 hotel rooms, 17 market condominiums, 16 deed restricted units (workforce), underground parking, and a restaurant and spa. The project includes a spa, fitness center, restaurant, and two rooftop decks in 190,000 square feet of habitable floor area.  

TIMING
-Planning Commission recommended Sketch Plan approval with 16 conditions: March 17, 2025
-Design Review Committee recomended Sketch Plan approval: March 11, 2025
-Sketch Plan presented to Town Council: April 21, 2025

COMMUNITY INPUT: Community members interested in knowing more about Mogul's project can contact Senior Planner, Tyler Valentine at tvalentine@jacksonwy.gov. Public comment is welcomed and can be provided in writing to the Planning Commission, Town Council electedofficials@jacksonwy.gov, or staff, or verbally at any scheduled public hearing. Agendas and meeting materials are available here with more information: https://www.jacksonwy.gov/491/Agendas-Minutes.

Lots 53, 57, & 58 in the Snow King Master Plan


ABOUT: Northworks Architects is requesting approval of development plans for Snow King Condos on Lots 53, 57, & 58. The plan for four buildings with underground parking includes space for 240 guests, 112,750 habitable square feet, 60 short-term rental condominiums, and 12 affordable deed-restricted condominiums. These lots are in the Lodging Overlay and Snow King Resort District so are not bound by the same regulations, in terms of maximum size, as other parts of Town. 

TIMING 
-Development Plan presented to Planning Commission: April 16, 2025

Teton County Justice Center at Simpson and King

 
ABOUT: This SPET-funded project will include demolition of the existing building. On the northeast corner of Simpson and King, this new building will provide courtroom, office, and detention center space. When built, it will house the Teton County Sheriff’s office and jail, the District Court office and Clerk of District Court, Circuit Court and the Clerk of Circuit Court, and the County and Prosecuting Attorneys. 

TIMING 
-Sketch Plan presented to Planning Commission: May 21, 2025 
-Sketch Plan presented to Town Council: June 16, 2025

Coming Soon

  • Browse ‘N Buy update presented to Design Review Committee in April
  • Hitching Post redevelopment coming soon

About The Town's Planning Process

New developments go through a number of approval steps before they can break ground. Applicants have pre-application meetings with the Town’s planning staff. Then, most applicants must submit Sketch Plans. These are processed by staff and only deemed ‘sufficient’ when complete. Then, staff write reports with related recommendations, and present Sketch Plans to the Design Review Committee (DRC) and then the Planning Commission (PC). 

Most, but not all, applicants must be approved by the Design Review Committee. All applicants go before the Planning Commission. After these reviews, Sketch Plans are presented to Town Council with recommendations from the DRC and PC. This process takes 4-5 months.

Town Council makes final decisions to approve, approve with conditions, or deny these plans. If Sketch Plans are approved, applicants create Development Plans and a second three-part process begins. Development Plans are reviewed by the DRC and PC and then presented to Town Council with recommendations from the other bodies. this process also takes 4-5 months and, again, Town Council makes final decisions to approve, approve with conditions, or deny applications.

Facebook Twitter Email

Other News in Town of Jackson

2026.02 Council Retreat

2026 Council Retreat Update

Posted on: February 3, 2026
20206 Newsletters

January 2026 Newsletter

Posted on: January 24, 2025
State of the Town News Flash

Open House: State of The Town

Posted on: January 23, 2026
Holiday Closure News  Flash (3)

Town Hall Closure

Posted on: December 23, 2025
Garage Change IG Post Voices (1080 x 1350 px)

Milward Garage Parking

Posted on: May 21, 2024
Board Opening News Flash

Volunteer Board Openings

Posted on: May 21, 2024
EPA Lead Line Invetory Flash (2)

EPA Water Line Inventory

Posted on: December 23, 2025